Only 32 of 40 new hospitals promised by Boris Johnson to be constructed by 2030 – and a few could also be too small, audit suggests

Jul 17, 2023 at 2:59 AM
Only 32 of 40 new hospitals promised by Boris Johnson to be constructed by 2030 – and a few could also be too small, audit suggests

The authorities is about to complete solely 32 of its promised new 40 hospitals by 2030 as a part of an over-budget and hard-to-deliver scheme, that may end in medical amenities which are “too small”, in accordance with a “damning” report.

The National Audit Office (NAO) has accomplished an investigation into the programme, initiated by the 2019 Conservative manifesto and reaffirmed in October 2020.

The report lays out myriad difficulties the federal government faces in finishing a promise first made by Boris Johnson and infrequently repeated by the Conservative Party since.

The investigation discovered the federal government is now set to overlook the 40 hospitals by 2030 pledge – with not less than eight amenities set to overlook the shut of the last decade goal, and it has additionally highlighted issues with a authorities plan to make use of mass-produced, preconstructed hospitals that would see sufferers unable to be handled.

Shadow well being secretary Wes Streeting branded the outcomes “shocking” and “damning”.

A map showing the location of the 40 new hospitals. Pic: National Audit Office
Image:
A map displaying the situation of the 40 new hospitals. Pic: National Audit Office

The promise

One of the central tenants of Mr Johnson’s 2019 election win was a pledge to construct 40 new hospitals.

Even on the time, there have been questions on what this truly meant and the way achievable it was.

In October 2020, Mr Johnson mentioned he needed to construct the brand new hospitals by 2030. In November 2020 Rishi Sunak – then chancellor – advised parliament they have been rising capital spending to “fund the biggest hospital building programme in a generation – building 40 new hospitals and upgrading 70 more”.

The NAO factors out that, after Mr Sunak made that announcement, the definition of a brand new hospital was modified to incorporate an entire new hospital, a brand new medical constructing or wing, or a significant refurbishment and alteration of “all but the main structure of an existing hospital”.

The audit additionally factors out that, on the time of Mr Johnson’s October dedication, “for most of the schemes the issue of affordability had not yet been considered”.

The report states the scheme to construct the 40 new hospitals by 2030 was all the time “likely” to vary the timescale or scope, and “this was not made clear to the public at the time”.

May 2023: Barclay insists 40 hospital target will be met

Health Secretary Steve Barclay at one of the few finished hospitals
Image:
Health Secretary Steve Barclay at one of many few completed hospitals

What is being constructed?

The scheme was initially cut up into 4 cohorts, though this was later expanded to 5.

A complete of 48 hospitals make up the cohorts, as there are eight amenities which already had plans in place.

Of the eight initiatives within the first cohort, just one counts in direction of the entire of 40 – as the opposite seven have been already in progress.

The different 4 cohorts aren’t set to begin development till not less than subsequent yr, with one of many cohort two initiatives additionally making up the eighth beforehand deliberate hospital.

Cohort three and onwards are set to make use of “hospital 2.0” pointers – the place blueprints of the hospitals and development are standardised and partially made off-site.

The plans for this undertaking haven’t but been revealed, and there are issues from the development sector about whether or not it will likely be possible to construct.

Furthermore, the NAO criticised a scarcity of transparency in how the 40 new initiatives have been chosen, saying there was “a failure in record keeping” and so they can not say how the hospitals have been chosen.

August 2022: Majority of 40 hospitals unlikely to be finished by next election

Prime Minister Boris Johnson meets with medical staff during a visit to Hexham General Hospital in Northumberland. Picture date: Monday November 8, 2021.
Image:
Boris Johnson promised the hospitals in 2019 and once more in 2020

Hospitals ‘too small’

As a part of its design for the brand new “hospital 2.0”, the federal government got here up with plans for what can be the minimal viable hospital – the most cost effective functioning facility.

But the NAO states that this specification dangers being “too small”, and the estimated capability of recent hospitals is predicated on assumptions that “may be unrealistic” in regards to the variety of individuals in a position to be moved out of hospitals for social care.

And estimates by the federal government that common stays will fall by 12% “seem poorly supported by the evidence”.

Furthermore, when the Department for Health and Social Care went to the Treasury for funding, it requested for £21.3bn, however was as a substitute given £18.5bn.

In order to search out financial savings, the federal government may have to maneuver much more schemes into the 2030s, or decrease the bottom specification of the new-style hospitals additional to economize, the NAO mentioned.

December 2021: Johnson accused of calling refurbishments ‘new hospitals’

Click to subscribe to the Sky News Daily wherever you get your podcasts

What are the delays?

One of the important thing components within the delays, in accordance with the NAO, is points with strengthened autoclaved aerated concrete.

This materials, used extensively, has now been discovered to be unsuitable for constructing previous round 30 years.

As introduced earlier this yr, an additional 5 hospitals with the concrete have been added to the brand new hospitals scheme.

According to the NAO, solely 32 of the beforehand promised hospitals will now be full by 2030 to create space for the brand new 5 initiatives – and the eight others will likely be completed within the subsequent decade.

Even this estimate is beneficiant, because it contains regenerating amenities not beforehand included and splitting one undertaking into two elements to up the figures from 31 to 32.

An absence of development contractors has additionally been raised – with infrastructure projects like HS2 and a scarcity of readability over what the designs will likely be inflicting uncertainty.

Handout photo dated August 2022 issued by HS2 of a aerial view of the HS2 Euston station construction site in London.
Image:
Projects like HS2 are taking over constructing assets

When will they be constructed, and the way a lot will it price?

The NAO has taken an estimate of prices and time frames.

Back in 2020, the federal government estimated it wanted between £20bn and £30bn to construct the 40 hospitals promised – plus the eight already began – by 2030.

It needed between £3.7bn and £16bn for the primary 5 years – and was given £3.7bn by the Treasury below Mr Sunak.

As such, a choice was taken to do smaller initiatives first and goal at finishing massive ones later within the decade.

In the primary three years, “slow progress” was made on the hospitals – however three opened by June of this yr, though none of them have been a part of the 40 new hospitals.

The different 5 suffered delays of between one and 16 months.

Cohort two was anticipated to begin in 2022, however as of May 2023 no constructing had began, though £11m of preconstruction work had taken place.

The first of the 40 new hospitals is predicted to open in late 2023, and the second in late 2025.

Cohorts three and 4 have been anticipated to begin in 2025, and the fifth later within the 2020s.

Now, the NAO reckons Cohort three won’t open till 2029 or 2030.

Please use Chrome browser for a extra accessible video participant

The state of the NHS defined

In phrases of price, each cohorts one and two have risen by nearly 50%, overrunning by a complete of £1.2bn.

On prime of the £3.7bn for the primary half of the 2020s, the Treasury has indicated it’s going to provide £18.5bn for the remainder of the scheme – however this was solely as much as 2031, and with the overrun more cash may turn into obtainable.

Inflation will even eat into the funds, and the NAO recommend the Treasury and well being division might need to renegotiate the budgets.

Gareth Davies, the top of the NAO, mentioned: “The programme has innovative plans to standardise hospital construction, delivering efficiencies and quality improvements. However, by the definition the government used in 2020 it will now deliver 32 rather than 40 new hospitals by 2030.

“Delivery up to now has been slower than anticipated, each on particular person schemes and in creating the hospital 2.0 template, which has delayed programme funding choices.

“There are some important lessons to be drawn for major programmes from the experience of the New Hospital Programme so far. These include strengthening the business case process to improve confidence on affordability and delivery dates, and improving transparency for key decisions.”

Please use Chrome browser for a extra accessible video participant

Blair on present state of NHS

Shadow well being secretary Wes Streeting mentioned: “This shocking report could not be more damning of the failing new hospitals programme.

“The so-called 40 new hospitals are over-budget, delayed, and could also be too small. Many aren’t ‘new’, others aren’t ‘hospitals’, and there aren’t 40 of them. In truth, only one hospital is on observe to be constructed by the subsequent election.”

A DHSC spokesperson said: “The NAO’s report acknowledges that regardless of modifications to the unique programme, 40 new hospitals are nonetheless anticipated to be delivered by 2030 and praises the programme’s revolutionary plans to standardise hospital development, ship efficiencies and enhance high quality.

“We remain firmly committed to delivering these hospitals, which are now expected to be backed by over £20bn of investment – helping to cut waiting lists so people can get the treatment they need quicker. Three new hospitals have already opened and more will open this year so patients and staff can benefit from major new hospital buildings, equipped with the latest technology.”